name: neqsim-equipment-cost-estimation
version: "1.0.0"
description: "Equipment-level CAPEX estimation — Turton/Peters/Ulrich/Seider correlations, CEPCI escalation, material/pressure factors, bare-module → grass-roots, AACE class 1–5, location factors, currency conversion. USE WHEN: a task requires a +30%/-30% Class-3/4 cost estimate at the equipment level (vessels, columns, pumps, compressors, HX, piping). Anchors on neqsim.process.costestimation.CostEstimationCalculator."
last_verified: "2026-04-26"
requires:
java_packages: [neqsim.process.costestimation]
---
# NeqSim Equipment Cost Estimation Skill
Class-3/4 (AACE 18R-97) order-of-magnitude → study estimates for individual
process equipment — the bridge between sized equipment and a project economics
model. Wraps Turton (5e), Peters–Timmerhaus, Ulrich, and Seider correlations
with CEPCI escalation, material factors, pressure factors, and Lang/Hand factors.
## When to Use
- Quickly cost a sized vessel, column, HX, pump, or compressor
- Build a **bare-module** → **total-module** → **grass-roots** stackup
- Apply CEPCI to escalate published correlations to current year
- Compare alternatives (e.g. centrifugal vs reciprocating compressor)
- Feed equipment cost into NPV / IRR via [`neqsim-field-economics`](../neqsim-field-economics/SKILL.md)
> For project-level economics, asset valuation, or fiscal regimes, use
> [`neqsim-field-economics`](../neqsim-field-economics/SKILL.md). This skill is
> equipment-scoped only.
## AACE Cost Estimate Classes
| Class | Maturity | Accuracy | Method |
| ----- | ------------- | ------------- | ----------------------------- |
| 5 | Concept | −50% / +100% | Capacity-factor (six-tenths) |
| 4 | Pre-FEED | −30% / +50% | Equipment-factored (this skill) |
| 3 | FEED | −20% / +30% | Sized equipment + bulk MTOs |
| 2 | Detailed | −15% / +20% | Detailed quantity takeoff |
| 1 | Final | −10% / +15% | Vendor quotes |
## Pattern 1 — Bare-module Cost for a Vessel
```java
import neqsim.process.costestimation.CostEstimationCalculator;
CostEstimationCalculator cost = new CostEstimationCalculator();
cost.setCurrentCepci(CostEstimationCalculator.CEPCI_2025); // 840
cost.setMaterialOfConstruction("SS316"); // sets Fm = 2.1
cost.setLocationByRegion("Norway"); // location factor
double shellWeight_kg = 8500.0; // from mechanical design
double designP_barg = 110.0;
double Cp = cost.calcVerticalVesselCost(shellWeight_kg);
double Cbm = cost.calcBareModuleCost(Cp, designP_barg); // applies Fp & Fm
double Ctm = cost.calcTotalModuleCost(Cbm); // + contingency + fees
double Cgr = cost.calcGrassRootsCost(Ctm); // + auxiliary facilities
```
## Pattern 2 — End-to-end via `calculateCostEstimate`
```java
cost.calculateCostEstimate(
Cp, // purchased equipment cost
designP_barg, // for Fp
shellWeight_kg, // for installation man-hours
"vertical_vessel" // equipment category
);
String json = cost.toJson(); // structured output for results.json
```
## Pattern 3 — CEPCI Escalation
```
C_today = C_published × CEPCI_today / CEPCI_published
```
Built-in indices: `CEPCI_2019` (607.5) through `CEPCI_2025` (840). Escalate any
literature correlation that's published with a base year.
## Pattern 4 — Equipment-Specific Methods
| Equipment | Method | Sizing input |
| ------------------------ | -------------------------------------- | --------------------- |
| Vertical pressure vessel | `calcVerticalVesselCost(weight_kg)` | shell weight |
| Horizontal vessel | `calcHorizontalVesselCost(weight_kg)` | shell weight |
| Distillation column | `calcColumnShellCost(weight_kg)` + `calcSieveTraysCost(D, N)` | weight + diameter + tray count |
| Shell-tube HX | `calcShellTubeHeatExchangerCost(area_m2)` | area |
| Plate HX | `calcPlateHeatExchangerCost(area_m2)` | area |
| Air cooler | `calcAirCoolerCost(area_m2)` | bare-tube area |
| Centrifugal pump | `calcCentrifugalPumpCost(power_kW)` | shaft power |
| Centrifugal compressor | `calcCentrifugalCompressorCost(power_kW)` | shaft power |
| Reciprocating compressor | `calcReciprocatingCompressorCost(power_kW)` | shaft power |
| Piping | `calcPipingCost(D_m, L_m, schedule)` | diameter, length |
| Control valve | `calcControlValveCost(Cv)` | Cv |
## Pattern 5 — Material and Pressure Factors (Turton)
```java
double Fp = CostEstimationCalculator.getPressureFactor(designP_barg); // ~1.0–3.0
// Fm constants: FM_CARBON_STEEL=1.0, FM_SS304=1.8, FM_SS316=2.1,
// FM_SS316L=2.3, FM_MONEL=3.2, FM_HASTELLOY_C=3.8, FM_TITANIUM=4.5
```
## Pattern 6 — Stackup Convention
```
Cp = purchased equipment, FOB factory (input)
Cbm = Cp × (B1 + B2 × Fm × Fp) bare module
Ctm = Cbm × 1.18 + contingency 15% + fees 3%
Cgr = Ctm × 1.30 + 30% auxiliary (utilities, storage, OSBL)
```
## Pattern 7 — Cost Estimate for a Whole Process
```java
double totalCgr = 0.0;
for (ProcessEquipmentInterface eq : process.getUnitOperations()) {
Cp = costForEquipment(eq, cost); // dispatch by type
cost.calculateCostEstimate(Cp, designP, weight, eqType);
totalCgr += cost.getGrassRootsCost();
}
```
## Common Mistakes
| Mistake | Fix |
| ------------------------------------------------- | ------------------------------------------------------------------- |
| Using outdated CEPCI | Always set `setCurrentCepci(CEPCI_<year>)` before calculating |
| Hardcoding Fm = 1 | Pick from `FM_*` constants based on actual material of construction |
| Missing pressure factor at high P | Use `getPressureFactor(P)` — silently × the cost at HP/HIPPS service |
| Reporting Cp as "installed cost" | Cp is FOB only; installed = at minimum Cbm |
| Mixing currencies | Use `setCurrency(code, rate)` then read all costs through `convertFromUSD/convertToUSD` |
| Claiming Class-3 accuracy on capacity-factored | Capacity factor (six-tenths) → Class 5; named in AACE 18R-97 |
| Ignoring location | `setLocationByRegion("Norway")` ≈ 1.3× US Gulf Coast for offshore |
## Validation Checklist
- [ ] CEPCI year matches the project base year
- [ ] Material of construction set per stream service (e.g. SS316L for wet sour)
- [ ] Pressure factor applied for design P > 10 barg
- [ ] AACE class declared in report (5/4/3) with stated accuracy band
- [ ] Stackup shown: Cp → Cbm → Ctm → Cgr with each multiplier
- [ ] Currency and location factor stated
- [ ] JSON saved via `cost.toJson()` to `results.json` under `capex` section
- [ ] Sensitivity to ±20% on key drivers (compressor power, column trays) reported
## Related Skills
- [`neqsim-field-economics`](../neqsim-field-economics/SKILL.md) — project NPV / IRR / fiscal
- [`neqsim-api-patterns`](../neqsim-api-patterns/SKILL.md) — `CompressorDesignFeasibilityReport` includes integrated cost
- [`neqsim-standards-lookup`](../neqsim-standards-lookup/SKILL.md) — AACE 18R-97